Recycling Yard Popovići
-
Name of the project
Recycling Yard Popovići
-
Project Details
Gross building area: 1.200 m2
-
Construction duration
Commencement date: August 2019
Completion date: February 2020 -
Location
Konavle
Project details
The facility consists of a covered area to accommodate equipment and staff, manipulative yard, and underground AB buildings for drainage and fire protection. The covered part has a total area of 400m2, made in a combination of masonry walls, facade panels and roof steel structures covered with sheet metal, while the asphalted manipulative yard has a total area of 800m2. The entire plateau of 1,200m2 was raised from the existing terrain by 4.00 m, in order to avoid flooding during the heavy rainy season. In addition to construction works, complete works on high and low electricity installations, fire alarms, water, drainage and hydrant networks were performed. The recycling yard is fully equipped for receiving and sorting various types of waste, and as such meets the needs of the local community.